7 steps from preparation to handover.
Follow the SNTGREEN RESERVE installation sequence, watch the details in the film and use the checklist at handover.
From laying to edge details.
Watch the narrated animation or use the chapter list to jump to a stage.
Go to the written steps
SNTGREEN · 4:48 · English narration. Educational animation showing green roof layers and the installation sequence; not a scaled construction detail. The dimensions in the film apply to the system shown and must be considered with your project details.
Read the video transcript
Waterproofing and roof falls
SNTGREEN green roof installation begins on a roof with completed waterproofing. The waterproofing is the essential protective layer that prevents water from entering the building. Before installing the green roof, always check the waterproofing and confirm that the roof has a suitable fall towards the roof drains.
Installing the root barrier
The root barrier helps prevent plant roots from reaching the waterproofing. Unroll the four-metre-wide sheet from the starting corner. Overlap adjacent sheets by fifty centimetres. Around the chimney and at the ends of each run, cut the sheet to fit the installation boundaries, leaving sufficient material for the wall upturns. Remove the offcuts from the work area.
Installing the protection fleece
The protection fleece shields the underlying sheets from mechanical damage during installation and from the layers placed above. Lay the two-metre-wide fleece over the root barrier. Allow a twenty-centimetre overlap at the joints. Around the chimney and at the ends of each run, cut the fleece to fit, retaining the material needed for the wall upturns. Remove the offcuts from the work area.
Wall upturns
Turn the root barrier and protection fleece up the parapet and chimney walls. The required upturn height depends on the finished growing-medium level and the approved termination detail.
Perimeter and chimney profiles
Edging profiles separate the planted area from the gravel protection strip. Before laying the drainage layer, install the profiles along two roof edges, working from the starting corner. Install four profiles around the chimney as well. Set the width between the wall and the profiles to suit the project requirements, local rainfall and climatic conditions. The horizontal foot of each L-shaped profile faces into the gravel protection strip.
Temporary restraint with gravel bags
Place bags of natural gravel on the horizontal feet of the profiles. The weight of the bags provides temporary restraint, keeping the profiles in position during installation. Do not empty the bags at this stage.
The role of the gravel protection strip
At a later stage, natural gravel is placed around the chimney, along the parapets and around the roof drains. These gravel protection strips help excess water reach the roof drains. They also provide access for inspection and for any future repairs to the waterproofing in these areas.
Preparing to lay SNTGREEN RESERVE
Once the root barrier, protection fleece and initial edging profiles are in place, installation of SNTGREEN RESERVE can begin. The installation shown uses rolls two metres wide and twenty metres long.
Unrolling the first sheet
Unroll the sheet over the protection fleece, starting at the corner. The openings of the water storage reservoirs face upwards.
The eight-centimetre flat edge
The eight-centimetre flat edge of SNTGREEN RESERVE remains on top. Place the adjacent sheet underneath this flat edge. Maintain the same overlap direction throughout installation.
Cutting to fit
Around the chimney and at the ends of each run, cut the product to fit the installation boundaries. Remove the offcuts from the work area.
Completing the perimeter profiles
As installation progresses, fit the edging profiles along the two remaining roof edges. The horizontal feet face into the gravel protection strip. Temporarily hold these profiles in place with bags of natural gravel as well.
The filter fleece: function and laying
The filter fleece limits the movement of fine particles from the growing medium into the drainage layer, while allowing water to pass through. Lay the fleece over SNTGREEN RESERVE. Overlap the joints by twenty centimetres.
Turning the filter fleece up at profiles
Turn the filter fleece up the face of the edging profiles on the planted side, and always extend it to the top edge. This limits the movement of growing medium into the gravel protection strip along the edges.
Gravel, growing medium and sedum
Create protection strips of natural gravel around the parapets, chimney and roof drains. Pour the specified growing medium into the planting area. Distribute the loose heaps, then spread and level the material evenly to the depth specified for the project. Next, lay the sedum cover in sections, side by side on the prepared surface. Bring the sections together to form a continuous plant cover. Other planting options may also be used, according to the project requirements.
Rainwater passing through the layers
Rain first reaches the vegetation. The water filters through the growing medium and filter fleece, then enters the SNTGREEN RESERVE layer.
How SNTGREEN RESERVE works
Some of the water is stored in the reservoirs of SNTGREEN RESERVE. Excess water travels along open drainage paths, through the openings in the profiles and across the gravel protection strip to the roof drains. In this way, SNTGREEN RESERVE combines water storage with the drainage of excess water.
This sequence applies to the SNTGREEN build-up shown in the video. Layers and joints may differ in special roof designs.
- 01
Complete roof preparation
Have the supporting structure, waterproofing, root protection and falls towards outlets checked. Plan material handling and temporary storage areas.
- 02
Lay the root barrier and protection fleece
Place the protection fleece above the root barrier. Complete joints, cuts and upturns at parapets and chimneys.
What to check at joints and corners - 03
Prepare the edging profiles
Place profiles along the first two edges and around the chimney on the protection fleece. Point their horizontal feet towards the gravel side and temporarily secure them with gravel bags, as in the film.
View the profile-to-gravel transition - 04
Install the RESERVE drainage sheet
Unroll with the reservoir openings facing upwards. Keep the flat edge on top, with the adjacent roll underneath. Complete cuts and the remaining edging profiles.
How do you check the laying direction? - 05
Complete the filter and edge upturns
Lay the filter over the drainage layer. Close the joints and turn the filter up the inner faces of the edging profiles. Check the surface before covering it.
What if the filter opens or tears? - 06
Place gravel, growing medium and plants
Create the gravel protection strips. Spread the growing medium to the specified depth and install the chosen planting. Keep roof drains accessible.
View the roof drain detail - 07
Check and hand over with a maintenance plan
Complete the handover list below. Give product and installation records to the person responsible for irrigation and maintenance.
How is maintenance continued after handover?
Final checklist
Tick the items in this session and print the list. It is not design approval or a certificate of conformity.